Perform a critical path analysis for the network and calculate the ES, EF, LS, and LF times.

need in 8 hours

Scheduling

For an organization, the following project schedule is given. Assume that all times are in days.

Task
Predecessor
Normal Time
Crash Time
Crash Cost Slope
A
None
7
7
NA
B
A
3
3
NA
C
A
8
4
600
D
A
4
4
NA
E
B
6
5
600
F
C, D
2
2
NA
G
E, F
6
6
NA
H
F
5
3
400
I
G, H
4
4
NA
J
I
2
2
NA

In a 3- to 4-page Microsoft Word document, address the following:

  • Draw the AON project network using Microsoft Project, Microsoft Visio, or some other tool capable of creating such a network. Perform a critical path analysis for the network and calculate the ES, EF, LS, and LF times.
  • Calculate the slack time for each activity.
  • Identify the critical path.
  • Assume that the organization will receive a $400 bonus for each day the duration of the project is shortened. The organization is also responsible for paying the crash cost associated with shortening the schedule. To maximize the net profit, identify which task you should crash and by how much.

Support your responses with examples.

Cite any sources in APA format.

Place a similar order with us or any form of academic custom essays related subject and it will be delivered within its deadline. All assignments are written from scratch based on the instructions which you will provide to ensure it is original and not plagiarized. Kindly use the calculator below to get your order cost; Do not hesitate to contact our support staff if you need any clarifications.

Type of paper Academic level Subject area
Number of pages Paper urgency Cost per page:
 Total:

Whatever level of paper you need – college, university, research paper, term paper or just a high school paper, you can safely place an order.