Would you recommend the acceptance of this proposal?

Clark Paints:  The production department has been investigating possible ways to trim total production costs. One possibility currently being examined is to make the paint cans instead of purchasing them. The equipment needed would cost $200,000, with a disposal value of $40,000, and would be able to produce 5,500,000 cans over the life of the machinery. The production department estimates that approximately 1,100,000 cans would be needed for each of the next 5 years.

 

The company would hire three new employees. These three individuals would be full-time employees working 2,000 hours per year and earning $12.00 per hour. They would also receive the same benefits as other production employees, 18% of wages in addition to $2,500 of health benefits.

 

It is estimated that the raw materials will cost 25¢ per can and that other variable costs would be 5¢ per can. Because there is currently unused space in the factory, no additional fixed costs would be incurred if this proposal is accepted.

 

It is expected that cans would cost 45¢ each if purchased from the current supplier. The company’s minimum rate of return (hurdle rate) has been determined to be 12% for all new projects, and the current tax rate of 35% is anticipated to remain unchanged. The pricing for a gallon of paint as well as number of units sold will not be affected by this decision. The unit-of-production depreciation method would be used if the new equipment is purchased.

 

Required: 

 

1. Based on the above information and using Excel, calculate the following items for this proposed equipment purchase.

 

    • Annual cash flows over the expected life of the equipment
    • Payback period
    • Annual rate of return
    • Net present value
    • Internal rate of return

 

2. Would you recommend the acceptance of this proposal? Why or why not. Prepare a short double-spaced Word paper elaborating and supporting your answer.

 

Note: A sample problem can be found in Doc Sharing (Word document instructions and Excel document solution).

 

Grading Rubric for Course Project (Part B)

 

Back to Top

 

Category Points % Description
Documentation and Formatting 10 9% Project worksheets will be done in Excel and will contain formulas to receive maximum credit. Work will be appropriately cited.
Organization and Cohesiveness 10 9% Calculations should be organized and correctly labeled. Also, for the Part B paper, a quality paper will include an introduction of the company and industry. In a quality project, the conclusion will summarize the strengths and weaknesses and their recommendations.
Editing 10 9% Quality work will be free of any spelling, punctuation, or grammatical errors. Sentences and paragraphs (where appropriate) will be clear, concise, and factually correct.
Content 80 73% A quality project will have all required work completed and will be correct.
Total 110 100% A quality paper will meet or exceed all of the above requirements.