Microsoft Project

Build using MSP an mpp file including a work breakdown structure and a Gantt chart showing the project critical path.
What does the critical path become if Task C takes three time units?

Task Predecessor(s) Time units required

A None 1

B A 2

C A 1

D B and C 1