Microsoft Project
Build using MSP an mpp file including a work breakdown structure and a Gantt chart showing the project critical path.
What does the critical path become if Task C takes three time units?
Task Predecessor(s) Time units required
A None 1
B A 2
C A 1
D B and C 1