systems analyst

You have been hired as a systems analyst. The project manager gave you the following network diagram and a matching table on the following page so that you can create a Gantt chart and a network diagram for the IS project. Since you are familiar with Microsoft Project as a project management software tool, you decided to use it to accomplish this task.

Requirements

1. Launch MS Project

o Go to Start button | All Programs | Microsoft Office | Microsoft Office Project

o If you get installation or error messages, then press Cancel.

2. On the first screen, select “Blank Project”.

3. Using Project, enter the following data:

o You may simply cut and paste the data from the table into Project one cell at a time, since pasting the entire table in one shot causes problems. Do not enter anything in the Start and Finish columns.

o If necessary, manipulate/move the center divider/split to show the five column headings below in Project.

Task Name Duration Start* Finish* Predecessors

Requirements Collection 1 mon

Screen Design 2 mon 1

Report Design 2 mon 1

Database Design 1 mon 2,3

User Documentation 2 mon 4

Programming 1 mon 4

Testing 0.5 mon 6

Installation 0.5 mon 5,7

. * The values for the Start and Finish dates are automatically filled by in Project.

Do not enter anything in them.

4. Right-mouse click on the right pane (where the timelines are shown), and select Nonworking Time | Middle Tier tab | under Middletier formatting, under Units: choose months. Repeat the same for the Bottom Tier tab | under Bottom tier formatting, under Units: choosemonths.

5. Go to the View tab | Task Views group, click Task Usage (top icon) to view the network diagram.