ZUMA Part 1

The ARC Company specializes in developing and selling a wide range of high-quality scooters. Sales representatives report that there is a growing demand for racing scooters. ARC’s president, Robin Lane, is excited about the possibilities and predicts that one day these kinds of razor scooters will be featured in X-Game events. ARC is a small company and uses a strong matrix to optimally utilize limited manpower.

The Project Priority Matrix for the Red Zuma Project is:

Time Scope Cost

Constrain X

Enhance X

Accept X

Part 1

You are a member of a project team assigned to develop the new razor scooter code named “Red Zuma.” Table A2.5 contains the information necessary to create a project schedule. For the purpose of this case assume the following:

TABLE A2.5 Red Zuma: Project Schedule

ID

Task Name

Duration

Predecessors

1

1 Red Zuma Project

260 days

2

1.1 Market Analysis

25 days

3

1.2 Product Design

30 days

2

4

1.3 Manufacturing Study

20 days

2

5

1.4 Product Design Selection

10 days

3, 4

6

1.5 Detailed Marketing Plan

15 days

5

7

1.6 Manufacturing Process

30 days

5

8

1.7 Detailed Product Design

45 days

5

9

1.8 Build Prototypes

25 days

8

10

1.9 Lab Test Prototypes

10 days

9

11

1.10 Field Test Prototypes

15 days

9

12

1.11 Finalized Product Design

20 days

7,10,11

13

1.12 Final Manufacturing Process

10 days

12

14

1.13 Order Components

7 days

12

15

1.14 Order Production Equipment

14 days

13

16

1.15 Install Production Equipment

35 days

14FS+20 days, 15FS+30 days

17

1.16 Celebrate

1 days

6, 16

Note: FS refers to a Finish-to-Start lag.

Page 647

The project begins January 2, 2015.
The following holidays are observed: January 1, Martin Luther King Day (third Monday in January), Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25.
If a holiday falls on a Saturday, then Friday will be given as an extra day off, and if it falls on a Sunday, then Monday will be given as a day off. If December 25th falls on a Friday then Monday will not be given a day off.
The project team works eight-hour days, Monday through Friday.

Construct a network schedule for this project and prepare a memo that answers the following questions:

When is the project estimated to be completed? How long will the project take?
What is the critical path for the project?
Which activity has the greatest amount of slack?
How sensitive is this network?
Identify two sensible milestones and explain your choices.

Include the following printouts:

A Gantt chart.

A network diagram highlighting the critical path.

A schedule table reporting ES, LS, EF, LF, and slack for each activity.
TAKE ADVANTAGE OF OUR PROMOTIONAL DISCOUNT DISPLAYED ON THE WEBSITE AND GET A DISCOUNT FOR YOUR PAPER NOW!